Cambridge solar

Cambridge solar

Between July 2013 and April 2015, we developed and delivered 69 MW of ground-mounted solar installation, in three phases on FC Palmer & Sons land, near Ely in Cambridge.

Stowbridge I:

The first phase of the project was commissioned in March 2014, comprising 24.3MW across 63 acres and over 79,000 panels.

Fenland and Green End:

Phases 2 and 3 of the project were delivered in March 2015, comprising 20.4 MW and 24.5 MW respectively, over 155 acres.
In total the three solar installations will export over 66 GWh of electricity each year, enough to power more than 15,000 households.

In addition to developing and delivering these plants, AGR continues to provide O&M services into the projects.